Practical Cutover Tips for Your Enterprise Project

on Monday, 03 June 2013. Posted in Enterprise Software , Blog

Practical Cutover Tips for Your Enterprise  Project

 

The cutover and go-live of an enterprise system must be well thought out;

An awareness campaign to the users should be launched 6 weeks in advance to prepare them for Go Live.

It includes awareness messages, the tasks to be carried out during system unavailability and other related information.

The implementation of Enterprise Software is almost always a massive operation that brings a lot of changes in the organization. Virtually every person in the organization is involved, whether they are part of the Functional or technical or the actual end users of the enterprise software.

Below I share tips and tricks on the critical last 6 weeks before going live in the areas of testing, data conversion, training and cutover validation.

Enterprise Cutover

Like always share your thoughts and feedback

More tips for production cutover to new system

http://appsconsultant.com/item/tips-for-enterprise-production-cutover-projects

Comments (7)

  • David Shaw

    David Shaw

    03 June 2013 at 21:08 |
    Good tips, I've bookmarked your site, I would add a detailed project plan when system is unavailable.
  • Martha

    Martha

    03 June 2013 at 21:38 |
    Thank you for sharing, great website! We are hoping to go live in about 2 months!
  • Lisa Nguyen

    Lisa Nguyen

    04 June 2013 at 20:08 |
    First time visitor found your website by Google search, bookmarked your site great content, I would also add do not underestimate the data migration steps that require to cleanup the data, most of us have regular functions and data cleanup activities, you must learn to juggle!
  • Pari Singh

    Pari Singh

    05 June 2013 at 04:18 |
    I would also add to make sure the cutover plan is available to all, before the cutover phase begins.
  • Matthew Perez

    Matthew Perez

    05 June 2013 at 14:09 |
    Excellent tips, Emphasize user training when adding new systems, to mitigate and avoid garbage in/out
  • Marc Chambers

    Marc Chambers

    05 June 2013 at 19:45 |
    Great information on cutover, thank you for sharing, I would add don't underestimate the 4 key activities of going to a new system, data migration, training, user acceptance testing and corporate system downtime.
  • Tom

    Tom

    07 June 2013 at 05:13 |
    Good info, also the system downtime add a 30 percent contigency on time, in my experiences most people provide a rosy estimate.